Wednesday, November 18, 2009
PM Views: In Search of Better Goals
Of the 10 project managers I was working with, 4 of them developed charters and scope statements indicating that the main objective was 'to reduce the FTE count in Department X by Y%.' Big flapping red flag!
Me: "Who are these FTEs?"
PM: "Well, some end users and some team members."
Me: "What happens when FTEs are reduced?"
PM: "People get packaged out."
Me: "How's the project going?"
PM: "Not very well. No one's too excited about it."
Me: "Wonder why ..."
To me, there is an intimate relationship between this kind of thinking and the economic dive of the past year. Money has been treated as the only asset and people are just a commodity. It's a 'killing the golden goose' thing.
Project managers can influence this kind of thinking for the better. Let's engage our sponsors and stakeholders in a dialogue about the big picture. What might be possible for our organization if, through our project, we could free some of our talent to pursue things of higher value? Why not make THAT a goal of the project rather than simply shaving some dollars off the expense column? The PMI Code of Ethics completely supports this approach. And doing so distinguishes us as more than managers. It demonstrates leadership.
Friday, November 6, 2009
PM Views: What is 'Communications' Again?
I feel about communications the same way I feel about the colour orange. Some days it seems like it's a colour all its own, but often enough it just seems to be a variation of red or a saturated yellow. And maybe that's it. Perhaps communication isn't so much a thing unto itself as it is a vehicle for, or enhancement of, something else.
When I'm really communicating with someone, I feel a sort of *click.* I can often see it in the other person as well. Something happens that is bigger than either of us. It is the most energizing part of managing projects for me - getting to the point of *getting it* so that my team and my stakeholders can share in project success.
Effective communications in projects is like model airplane glue. Applied well, you don't really notice it in the end product. Used sloppily, you end up with gobs of glue all over the place. Sure, the airplane is held together, but it's best to stand back a few feet so you don't notice the disaster of the execution. And if I spend too much time around communications *templates* I start to hallucinate anyway.
Monday, September 28, 2009
PM Stories: High-Risk Advocating
As project manager, I needed to address two contradicting positions. First, my team needed to feel that their concern about the deadline was taken seriously. An unheard attitude of “we’re not going to meet the deadline” can become a self-fulfilling prophecy. I didn’t want us to subconsciously undermine efforts to succeed in order to prove that our predictions were right. My team needed to be confident that I was communicating the schedule risk appropriately.
Second, I wanted our sponsor to be confident that every effort was being made. If I simply informed them that we were projecting a schedule overrun, the sponsor would likely have implemented their own strategies to meet the date - completely understandable even if it was a long shot. I communicated status using a blend of progress (what we’ve done) with a qualitative assessment of its impact on schedule risk. Next, I laid out our forecast (what we’ll do), again with prediction of risk impact.
In the end, we didn’t launch at the scheduled event (you thought I was going to claim success?). In a way though, we were successful. The development team had flown to the client site, and both sponsor and team felt that all efforts had been made to meet the deadline. The sponsor was not caught by surprise because they had been kept up-to-date concerning risks all along. Eight hours before the event, the sponsor rescheduled the planned launch, perhaps not thrilled, but satisfied with the team’s commitment to the sponsor’s goal. Everyone ended up on the same page.
Moral: A project manager’s ability to advocate for both sponsor and team makes it possible for those with differing interests to work toward a common goal.
Wednesday, August 19, 2009
PM Practice: Tips for Tasks
Sorry … I should say ‘activities’ … not tasks. Pardon my non-PMI-speak.
Early in my coaching career, I worked with a bright project manager on developing his schedule. We talked a little about how to create a WBS and then how to define activities. I gave him those steps as an assignment and left him to it. When we met again, I was surprised to discover that he had no idea how to structure work. His activities ebbed and flowed in different directions. Some bore no relationship to the project, while others seemed to bleed into each other. Imagine defining activities for a dinner party. This fellow would have included activities like:
- “Prepare ingredients in the fridge” (what about the ones in the cupboard),
- “Buy and broil meat” (is that all you are buying … and aren’t there a couple activities in there?)
- “Bring salad to the table holding bowl with 2 hands” (the 2 hands part is a specification, not an activity).
Since then, I have thought more carefully about how I actually define activities so that I can talk about it to the less systematic among us (a group I identify with more as I get older). Apart from saying ‘it looks weird,’ here are some tips that have helped:
- Activities involving performing work. It follows then, that activities should be structured using a verb-noun structure, as in “Do Something.” I worked with an event planning team that included activities like “Hotel.” I asked if they were planning to book it or build it.
- Team members should be able to agree on what done looks like. Most people would say that “Write Draft Document” would end with an essentially-complete first pass at the deliverable, so that’s a good one. “Conduct Research” is trickier. Adding some specifications as a note to your activity may help.
- Completing the effort associated with an activity should move the project measurably forward. “Execute Test Plan” should yield a performance result. I saw a plan once with an activity called “Develop Team.” I suggested they change it to “Hold Team Spa Day.” At least you know there’s no going back once you’ve had sweated it out in a sauna with your analyst.
- Activities can be big or small. There is no hard and fast rule here, but I like each team member to focus on between 1 and 3 activities in a week, plus 1 project administration activity that remains open for the duration of the project. This usually means that activities will range between 8 and 60 hours of effort. Activities that are too small lead to administrative overload when you collect actuals from your team each week (which of course you do …). Activities that are too large are difficult to monitor for progress. “Create Requirements Document” can be a 6 to 8 week process with only 1 measureable deliverable at the end. Without a near-term checkpoint, activities like this long tend to get longer. I was brought into a project once that had spent 12 months on requirements for a supposedly 18-month project. I would break this activity into a set of iterations of draft and review.
- If the effort transitions from 1 person to another, that’s probably a new task. “Write …” is one task. “Review …” is another.
- A waiting time often signifies a break in tasks. Keep this in mind with projects that involve paint or concrete.
Activities are foundational to project monitoring and control. Getting a solid model of defined activities for the project will pay off later with fewer gaps or overlaps in scope and the team’s improved ability to deliver to expectations.
Tuesday, July 21, 2009
PM Practice: Using Milestones
It was easy to spot from a distance, but it didn’t take up much space. The face of it was inscribed with one number indicating where we were on the path and a 2nd number informing travelers how far it was to the next major town. As we walked along the path, we were either moving towards it or, having passed it, moving away from it. The time that we spent ‘at’ the milestone was maybe a second. The parallels to project milestones make it clear why these ‘moments on the path’ share the same moniker:
- Milestones provide a clear measure of progress and are uniformly visible to all stakeholders. When you pass the ‘Design Complete’ milestone, pencils go down and girders go up. If you’ve still got a pencil in your hand, you haven’t passed the milestone yet.
- Milestones have no effort associated with them. Tasks do. ‘Design Complete’ is a milestone. ‘Complete Design’ is a task.
- Milestones have no duration. They’re just markers on a path. If you stop to marvel at your accomplishments upon reaching a milestone, fine - many people do. But that’s a task (‘Admire Progress’) that has nothing to do with the milestone.
- Milestones are either 0% or 100% complete. There is no ‘50% complete’ for milestones. Once you complete all the tasks needed to reach the milestone, the milestone is passed. Until then, keep working.
- Different milestones may hold the interest of different stakeholders. ‘Key’ milestones are of interest to everyone and often associated with either a major deliverable (‘Test Case Creation Complete’) or a change of the project phase (‘Testing Complete’).
- Milestones are placed with reasonable regularity. I aim for some kind of milestone about every 4 to 6 weeks. Agile Project Management leans heavily on this idea because sponsors need only commit to the process incrementally.
- Key Milestones are on the critical path. As a communication tool for progress, they work better when they don’t wobble around due to float.
Some milestones existing today have been in place for centuries, yet still convey accurate information (Stockholm hasn’t moved). They tend to be stable. Project milestones are similar.
Thursday, July 9, 2009
PM Laws: Who Defines Project Success?
I'll ask them to tell me about a successful project and what it was that made it a success. I hear lots of reasons such as a great team, got to use new technology, build what 'I' wanted, requirements didn't change, ... When I ask why the sponsor or key stakeholders thought the project was successful, the confusion sets in. Some team members tell me that the sponsor was not happy with their successful project. More commonly, they simply don't know whether stakeholders considered the project a success or not.
This perplexes me. How is it possible for team members not to know what their stakeholders think about the project? This form of 'tone deafness' is a huge risk for project failure.
It's completely fine to be proud of the work we've done on projects, to enjoy being part of a particular team, or to get a chance to work on something really new. In the end, however, the success of any project will be defined and judged by those that initiated and paid for it. Just keeping this on the team radar goes a long way to ensure that the work being done is moving the project towards success.
So, the project you just finished ... was it a success? Says who?
Thursday, July 2, 2009
PM Views: Chaos in Project HR
Why would this be? The talent management folks I've met are just like other parts of the organization. There are enough inspiring, capable individuals sprinkled among the discipline that it should be possible to do better. Maybe the size of the failure hints at the complexity of the challenge? Think about this:
- There is reasonable evidence that 'superior' work performance can be predicted (though not perfectly) based on a combination of raw mental horsepower coupled with a set of about 20 competencies (e.g., results orientation, resourcefulness, ...). Personality tests may not predict work performance so well, but can provide clues about related factors such as whether your Einstein will show up or not.
- The overwhelming majority of recruitment and selection processes in organizations focus on education, experience, and technical knowledge. The predictive ability of these factors is much weaker than competencies.
It's amazing how often I hear HR staff claim that they need a project manager with knowledge of 'System X' because they need to be able to talk to the programmers on the team. I may be way off base here, but that sounds like a communication competency, not a technical one. I've managed many a project (successfully) where I didn't understand the ins-and-outs of the technology, but I could pick up on when one of my team was concerned about something. In fact, thinking back to my project management failures, it has been on projects where I understood the content deeply - perhaps to the point where I took my eye off the management ball.
So why is HR talent management so completely focused on the wrong things? Competencies are extremely intricate and challenging to assess. It's also expensive, though not as expensive as making the wrong choice for your organization. Experience and technical knowledge assessment on the other hand can be automated (or as I like to say, 'commoditized'). And during high-supply economies like 2009, the push to emphasize throughput over value is even stronger. Unfortunately, a lot of companies are simply missing the best individual faster ... and it peels dollars you don't see right off your top line.
